Malaysia’s latest
competitive bidding exercise for combined cycle gas turbine (CCGT) power plants
— the second in two years — saw five submissions at its close on July 1. [This
article is based on The Edge Malaysia report (13 July 2026)]
The Energy Commission
requested for proposals with the aim of seeing new plants start operations
between 2029 and 2031 as part of a repowering exercise as old plants are
retired and electricity demand continues to grow strongly, driven by rising
electrification and the influx of data centre projects.
Notable players include
a consortium involving YTL Power International Bhd with 750mw planned in Pulau
Indah, Klang and a joint venture (JV) between Petroliam Nasional Bhd (PETRONAS)
and Edra Power Holdings Sdn Bhd (700mw).
It is understood that
utility giant Tenaga Nasional Bhd has also submitted a bid for a 700mw gas
plant project in Connaught Bridge, Klang. The location was home to one of the
oldest power plants in the country with an 800mw-capacity plant, which has
since been decommissioned. The location currently houses a smaller, 375mw power
plant that will operate until 2037.
According to a source,
Genting Bhd, through its power unit, has also submitted a 1,400mw proposal in
Gebeng, Pahang.
This latest bidding
round, dubbed NEWGEN26, comes on the heels of an earlier bidding exercise in
2025 (NEWGEN25) that saw a Tenaga JV with Aurora Power Generation Sdn Bhd being
the sole winner of new project awards with 1,400mw capacity in Terengganu under
a 15-year power purchase agreement (PPA).
Under the 2025
exercise, the Energy Commission also awarded a PPA extension to three companies
for their existing plants, namely Tenaga (1,262mw), Malakoff Corp Bhd (2,082mw)
and Edra Power (1,375mw) to end-2029 and early 2030. PETRONAS, meanwhile, secured
a 150mw additional capacity for its power plant in Pengerang, Johor.
Peninsular Malaysia
could see as much as 7,848mw of new gas power plant capacity between 2029 and
2031. In the same period, as much as 6,930mw worth of coal and gas-fired power
plant capacity could retire. The bulk of the plant retirement would come from
coal, comprising the nearly 1,475mw Sultan Aziz Power Station in Kapar, which
is 60:40-owned by Tenaga and Malakoff (retiring in July 2029); the 2,070mw
Janamanjung plant in Perak, owned by Tenaga (August 2030); and the 2,100mw
Tanjung Bin power plant that is 90%-owned by Malakoff (September 2031).
The idea is to phase
out coal and replace it with gas-fired plants as baseload and reduce emissions
in line with the government’s commitment to international practices. However,
the influx of gas-fired power plant developments globally — to meet rising
electrification demand while managing emissions — has resulted in a market
squeeze for gas turbines, in some cases, requiring down payment of up to
one-third of the turbine’s price.
It is understood that
YTL Power is among the few players that have secured turbines for new bids.
Malakoff, which is said to be close to securing two 1,400mw power plants,
previously announced it had secured four turbines from Mitsubishi Power Ltd.
Tenaga, which has the NEWGEN25 1,400mw tender win in Terengganu and another
1,400mw project in the state, said a month ago that it had signed an agreement
for six gas turbines, also from Mitsubishi Power, with up to 4,200mw capacity.
However, the lead time
remains tight for new projects. According to Wood Mackenzie, gas turbine
manufacturing backlogs have stretched power plant lead times to as long as five
years, compared to 3½ years previously.
Attention has centred
on data centres (DCs), which currently account for 7% of electricity demand in
Peninsular Malaysia. This is expected to rise to 31% by 2035 on a power grid
that also needs to cater to growing demand from other commercial and residential
users.
Prime Minister Datuk
Seri Anwar Ibrahim has said Malaysia is restricting new DC projects that are
not linked to artificial intelligence to manage water and electricity
consumption. As a medium-term measure, the government has conducted two tenders
for new gas-fired power plants — last year and this year — to add to generation
capacity.
However, actual DC
consumption today is at a low base: it represents just 54% of approved
capacity, with the remaining 948mw expected to largely come online only by
2028. That alone is equivalent to about 3% of grid-connected installed
generation capacity, excluding other projects approved but not commissioned
yet.

Based on the latest
peak grid demand of 21,583mw on June 8 and grid-connected installed generation
capacity of 28,192mw in 2025, Peninsular Malaysia has a seemingly comfortable
reserve margin of 23.4%.
But a closer look shows
available generation currently stands at just under 25,000mw, narrowing the
margin to around 13%. The reduction is partly due to planned outages for
maintenance works, including at the 2,242mw Edra Melaka Power Plant. It is the
largest thermal power plant in the country.
Peninsular Malaysia
also saw heightened electricity imports of 300mw from Thailand, mainly between
September and November 2025 and throughout June this year, Grid System Operator
(GSO) data shows.
Renewable energy
generation, mainly from solar and hydro, is intermittent in nature and accounts
for about 12% of peak demand, according to a snapshot of grid demand. On July
9. large-scale solar (LSS) supplied around 1,500mw during the day, while hydro generation
exceeded 1,100mw at night. Hydro also supplied between 300mw and 600mw at other
times of the day.
In terms of
grid-connected installed generation capacity, LSS and hydro represent nearly
17% of the total. LSS totalled 2,237mw as at July 2025, compared with 2,526mw
of hydro generation, according to Energy Commission and GSO data.
Another 2,400mw of
solar capacity sits at the distribution network level and is therefore not
counted as part of grid demand. Meanwhile, oil- and diesel-fired plants
continue to supply between 360mw and 450mw.
In the short term, the
government has allowed several gas power plants to operate beyond their
original commissioning periods. Will new gas plants be ready to offset the next
coal power plant to be decommissioned — totalling 1,474mw — in 2029? The question
is no longer whether Malaysia has enough power today, but whether new
generation can come online fast enough or it has to play catch-up. Will the
phasing-out of coal, which is the base load now for power generation, make it
even more challenging?
Reference:
Second gas power plant
RFP in two years said to have drawn five bids, Adam Aziz / The Edge Malaysia, 20 Jul 2026